1st step is to make sure ...

Published by

1st step is to make sure that you are aware of the pipe network in the campus. If possible try to get the latest drawings.

Next, identify the main branches / inter connections to understand how flow is distributed.

Check if flow meters are available in these locations. If available, then it's easy mathematics for you to understand if water supplied is received at customer end. If not, arrange for bulk meters & hen do the calculations. If you have budget constraint arrange for temporary metering solutions like Ultrasonic meter. It may not e accurate,, but definitely will give you a volume to start with

 

 