Hi, this is akin to asking ...

Published by

Hi, this is akin to asking how long a piece of string is. A lot more detail is reuitred to answer this question. For example; 1. Volume to be processed (required flow rate)? 2. What is the effluent? 3. what level does the effluent need to be processed to?

These are just a few of a myriad of questions that need to be asked before any idea of Capex or Opex can be arrived at.

 

1 Comment

I am trying to design for hotel wastewater. The flow in the hotel ranges from 4 cum/day to 250 cum/day. The effluent quality is to get <30 BOD for reusing treated wastewater in irrigation. I would be grateful if you can provide any reference for the cost calculation