Hello ,louiri the focus of ...
Published by Geovanny Michelen
Hello ,louiri the focus of the task is clear which is to transfer storm water pre screened at 5mm to N number of meters ,
Its been stated the following :
Start of route at the existing pump station and end of route - existing storage tank . Are you changing the route , pipe network or else ?
1 Comment
Hi Geovanny, this is a new pipe to transfer storm water from the existing PS to the existing tank. Addition to the existing storm water harvesting scheme to increase supply.
Published by Iouri Vaisman, IVS Pty Ltd - Director