Hi There This method is ...
Published by Azrin Kasman, Operations Manager at Muscat City Desalination Company
Hi There
This method is being used by most SWRO Plant Operator
Specific Energy Consumption (S.P.C) = Energy Consumed (KwH) / Product Water Produced (m3/Day)
Let Say you plant is producing 136MLD and the Total Energy consumed per Day for the Plant is 459 MWH
So your Plant SPC should be - (459 x 1000) / (136 x 1000) = 3.375 kwh/m3